Annex
|
Component |
Current Status |
Recommendations |
Cost |
|
General Exterior |
The annex was built in 1995. It is a three-story, brick 21,000 square foot facility. P1, P2, P3, P4. The third floor has a skywalk that connects the annex to the second floor of the main courthouse. |
|
|
|
Exterior Walls |
The exterior brick walls of the courthouse are in excellent condition. There is no visible evidence of damage or wear. |
|
|
|
Roof |
It is constructed of metal roofing materials and is pitched. It is in excellent condition. |
|
|
|
Windows and Doors |
The windows are double glazed with vinyl-clad aluminum. P5. |
|
|
|
|
There is on-street handicap parking available in front of
the courthouse and is well labeled. P10. A handicap
accessible entrance is available through the annex, and a sky way connects
the annex to the main courthouse. The handicap accessible restrooms in the
annex meet all |
|
|
|
Fire Safety |
The annex is up-to-date with all fire code regulations. |
|
|
Structure
|
The interior of the annex is in excellent condition. P6, P7. |
|
|
|
Security |
There is no security alarm system or cameras. |
Restrict all access to the building to the main entrance to the Annex. Install a magnetometer and an X-ray machine Install security system. Install ballistic material at the bench in the Magistrate’s Courtroom. |
$40,000 $5,000 $1,500 |
|
Electrical |
See attached table for individualized items. All units are in good condition. |
|
|
|
Mechanical |
See table below for each individual unit. All units are in good condition |
|
|
|
Work Safety |
The annex is up-to-date with no apparent problems or code violations. |
|
|
|
Space requirements |
More storage space for documents is needed. The former jail is being used for the |
Convert the second floor of the former jail to a storage area for documents from the courthouse. In addition, we recommend adding 5000 square feet of storage space for storage of documents. |
$80,000 $270,000 |
|
Subtotal |
|
|
$396,500 |
|
Soft Costs |
Professional fees, permits, surveys, and studies |
20% |
79,300 |
|
Total |
|
|
$475,800 |