Taylor County Courthouse Detail Report
|
Component |
Current
Status |
Recommendations |
Cost
|
|
General
Exterior |
The
original date of the courthouse construction was 1900 (P1, P3, P4, P5, P7,
P8,
P9,
P11). The annex (attached to the courthouse) was
constructed in 1976. The approximate
size of the courthouse was not known, but it is three stories with basement,
and towers. The annex attached to the
courthouse is in very good shape, with no major problems reported (P23, P26). This building is on the Historical
Register. |
The
building is a mixture of styles and materials. The original courthouse is
grand with beautiful brown brick and stonework. It looks as if there was an earlier red
brick addition prior to the fluted concrete block annex attached to the
back. We recommend cleaning and
restoring the façade of the original structure and brining the entire
building up to code. |
|
|
Exterior
Walls |
The foundation of the annex is concrete and the
courthouse is stone. The walls of the
annex is split faced block and the courthouse is brick. There is no visible settlement of the
foundations. The walls of the courthouse building are in poor condition, with
some cracks in the walls located on the back and right sides of the
building. There is also some evidence
of water damage and pealing paint on the front of the courthouse, (P7,
P8,
P9). The exterior walls of the annex show
evidence of cracking in the stairway (P52,
P53,
P54). |
Clean
and restore the old courthouse and repair the cracks. Perform
an engineering study of the cracks in the stairwell Remove
the paint from the masonry. |
$35,000 $3,000 $10,000 |
|
Roof |
The
roof on the courthouse is a pitched slope with shingles. It was replaced more than ten years ago ( P11). The annex roof is rubber membrane with a
low slope and is good condition. They
stated that they are pursuing bid contracts for the replacement of the
courthouse and jail roofs because of their poor condition. |
Replace
the roof of the courthouse with period appropriate shingles. |
$75,000 |
|
Windows
and Doors |
The
windows throughout the annex are in very good condition, they are fixed,
double pane, aluminum frame windows, (P61, P62). Some of the courthouses windows are new
double pane, aluminum frame windows, in very good condition, (P1, P13). The other windows are wood frame, single
pain, double sash in very poor condition with missing and damaged
caulking. The
main door for the courthouse is aluminum frame with single pane glass. The other door is a steel door with a
window, (P17,
P44). The doors for the annex are aluminum frame
with single pane glass, In good shape (P21). |
Replace
the windows in the courthouse with historic sashes. Replace
a door in the courthouse. |
$75,000 $1,500 |
|
Fire
Safety |
The
courthouse and annex contained exit signs, which were all visible and in the
proper areas for maximum visibility. The courthouse and annex do not have
sprinklers. The fire alarm annunciator
panel for the courthouse and annex is located at the front entrance to the
annex and was in proper working order.
There are two enclosed fire exit staircases in the annex, which exit
through a properly marked exit route.
The main staircases in the courthouse are open to the second floor and
both exit to the first floor where an outside exit is easily accessible, (P48, P49). The staircase into the records office has
exits available to the outside from the records room itself, (P47). One of the two emergency only exit doors
located in the records room is blocked by a steel door that would not allow
anyone to exit if a fire would take place.
The only room that is able to hold fifty or more people has two
properly marked exits and panic hardware on the doors, (P50, P51). None of the exits for the annex and
courthouse have panic hardware on the doors except in the courtroom. Both buildings have horns, strobes and fire
detection equipment located in the proper areas of the room, halls, stairs,
and exit doors. |
Enclose
the top of the stairs on either side the second floor with fire wall and fire
doors. Install
a sprinkler system throughout the building. |
$2500 $130,000 |
|
ADA |
The
courthouse Annex building has a parking space in the street in front of the
building with a curb cut in the sidewalk directly beside the parking space (P18). The front entry is accessible from the
sidewalk and has a powered entry door (P20,
P21). The annex has an elevator and the old
courthouse is accessible from the attached annex building. There
are accessible restrooms on the first (P28,
P29)
and second floor (P39). These rooms appear to be compliant but lack
insulation on the hot water and drain lines. The
doors throughout the building do not have lever handles or ADA compliant
signage. The
courtroom does not have a wheelchair lift on the witness stand. |
The
accessible parking space does not comply with ADA. If a person in a wheelchair parks in the
space they will block the curb ramp! We recommend a new Parking space off the
street. Insulate
waterlines and drain lines Install
new lever handles Install
new signage Install
witness stand/Judges bench lift. |
$3,000 $100 $7,500 $1,200 $18,000 |
Structure
|
There
is some stair-step cracking in the back staircase of the annex, (P52,
P53,
P54). In addition, there is some water damage in
the staircase area leading into the records basement, (P45, P46). |
See
note above on exterior walls. |
|
|
Security |
There
is closed circuit television in both the annex and courthouse. There were no
metal detectors located in either building.
No guards were present at either location. |
This
facility should have an entry-level screening using a walk-through metal
detector and an x-ray machine. All
perimeter doors not being used for entry-level screening should be used for
emergency exits only. These doors
should also be secured by installing an audible alarm, magnetic contacts, and
a crash bar. Duress
alarms should be installed beneath the judge’s desk, secretary’s desk,
judge’s bench in the courtroom, hearing table in the jury room, and the
clerk’s desk. The family court judges should be provided with a duress alarm.
The adult and juvenile probation officers should have duress alarms installed
at their desks and at the receptionist’s desk. Duress alarms should be
installed beneath the prosecuting attorney’s desk, beneath the receptionist’s
desk, and beneath the table in the conference room. Two duress alarms should
be installed, one beneath the front counter and one beneath an office desk.
Duress alarms should be installed beneath the magistrates’ desks magistrates’
assistants’ desks, and the bench in the courtroom. Prosecution
and defense witnesses should have separate witness rooms and rest rooms to
avoid threats and assaults. The
judge’s bench and clerk’s desk should be protected on the front and sides
that have public exposure with ballistic material. All
light switches should be replaced with key-controlled switches, and breaker
boxes should be locked. A
phone line should be installed to provide the court and the staff with
outside communication in case of power failure. Window
glass tinting should be applied to eliminate outside view through the windows
in the courtroom and jury room. The
tint should be dark enough to prevent someone from viewing the occupants
during nighttime hours. Remove,
trim, or cut down any bush, shrubbery, or trees surrounding the courthouse and
parking lot which may provide cover to an assailant. |
$40,000 $7,500 $3,600 $30,000 $3,000 $1,500 $600 $1,200 |
|
Electrical |
The
main electrical service for the annex and courthouse comes into the mechanical
room and into a Westinghouse service box, 3 phase / 4 wire, 120/240 V, 800 A
main, which is in very good condition.
The communications for the annex and courthouse are housed in the
mechanical / electrical room of the annex and are in good condition. The room is being used for storage, which
poses a fire hazard. These items
should be removed. The
interior lighting of each building for the rooms is adequate, but in the
hallways of the courthouse and the stairwells of the annex, the lighting is
very poor (P56). |
We
recommend that the lighting situation in the courthouse halls and annex
stairwells be improved with more fixtures. |
$6000 |
|
Mechanical |
The
annex and the courthouse are both serviced by a Burnham Gas Fired boiler,
model #606, (P72). There is one circulating pump (mfg.
Unknown), model #4QC56B17D84BP. A
Trane interior air handler in the annex, model TWE060A300BB, with a Trane
condenser located just outside the mechanical room, handles cooling. There is one fan coil located in each room
of the annex but it was stated that they might not be in operation any
longer. All cooling in the courthouse
was handled by window units. |
We
recommend a central air handling system be installed in the courthouse for
aesthetics and energy efficiency. |
$ 200,000 |
|
Work
Safety |
No
problems were noted. |
|
|
|
Space
requirements |
They
would like to renovate the jail in three years when the new regional jail is
completed and they will no longer house prisoners. |
We
recommend the jail be renovated for storage. |
|
|
Subtotal |
|
|
$655,200 |
|
Soft
Costs |
Professional
fees, permits, surveys, and studies |
20%
of total |
$131,040 |
|
Total
Cost |
|
|
$786,240 |