Ohio County
Old AEP Building Detail Report
|
Component |
Current Status |
Recommendations |
Cost |
|
General Exterior |
The building has 5 floors plus a basement and an attic, which houses some mechanical equipment, (P1, P2, P3). It is in fair to good condition. It has a red brick masonry exterior with stone accents. |
|
|
|
Exterior Walls |
The stone on the exterior seems to be discolored. There are some damaged bricks in some areas of building, (P4). There is some missing mortar, (P5). |
Clean the brick and stone, re-point the brick, and seal. |
$180,000 |
|
Roof |
The building has a flat rubber membrane roof. It is relatively new and in good condition, (P6). |
|
|
|
Windows and Doors |
The windows are metal frames in good condition, (P1). The doors are glass and aluminum. They also are in good condition, (P7). |
|
|
|
Fire Safety |
The fire safety systems in the building appear to be under renovation. There are fire alarms with strobes on some floor, (P11, P12). |
|
|
ADA Compliance
|
The building is currently under renovation. Where the renovation has been done the ADA compliance is very good. The bathrooms are in good condition, (P8, P9). There is an elevator. |
|
|
Structure
|
There were no structural problems noted. |
|
|
|
Security |
The security at the main entrance consists of a deputy and a metal detector. The building houses the family court system and therefore requires more security.
|
Provide limited access control for the building with the following: X-ray machine Card access for employee entrances Closed circuit TV Cameras Ballistic material for bench Duress buttons Alarmed exit doors Security Console |
$35,000 $12,000 $20,000 $ 1,500 $ 2,000 $ 4,500 $40,000 |
|
Electrical |
The electrical is a mix, some modern breaker boxes, some older breaker boxes\electrical panels. There is remodeling going on throughout the building in various phases (seems to be a floor at a time). |
The electrical renovations should continue to bring the building up to code. |
|
|
Mechanical |
The mechanical systems all appear to be under renovation. There is a mix of new and old equipment.
|
|
|
|
Work Safety |
There was some exposed wiring which could be a hazard dependent upon if the floor was occupied or not, (P10).
|
The electrical renovations should continue to bring the building up to code. |
|
|
Space requirements |
Completion of the remodeling to the rest of the floors should provide the county with the storage and office space needed.
|
Complete renovation of the AEP building |
$1,965,000 |
|
Subtotal |
|
|
$2,260,000 |
|
Soft Costs |
Professional fees, permits, surveys and studies |
20% |
452,000 |
|
Total |
|
|
2,712,000 |