Morgan County Tax Office Detail Report

 

Component

Current Status

Recommendations

Cost

General Exterior

The tax office is a two story building with a basement, (P1, P2, P3, P4).  It has a block of foundation with no evidence of settlement.  There is a water leakage problem, (P5).

 

The basement should be waterproofed to prevent water infiltration.

$15,000

Exterior Walls

The brick walls are in good condition with no water damage.

 

 

 

Roof

The flat roof has a rubber membrane and appears to be in good condition, (P6)

 

 

 

Windows and Doors

The windows are single pane wood windows.  They are in good condition.  The wooden doors appear to be in good condition as well.

 

 

 

Fire Safety

There are no fire alarms, sprinklers, exit lights, or emergency lighting.  The stairs not enclosed and are blocked, (P7).  The material stored around and beneath the stairwells should be removed for fire safety.  There is no panic hardware on the doors and they do not swing outward.  There are not two means of egress from each floor.

 

Install:

Fire alarm system.

New steel doors with panic hardware.

Exit and emergency lights.

Second interior stairway during renovation.

 

 

$5,000

$3,000

$4,500

$10,000

ADA Compliance

Uses same parking as CH, no public areas except for reception area, no ADA bathroom, will be updated during renovation.

 

Add an accessible parking space.

 

Provide an ADA compliant bathroom.

 

Install a ramp to the building

 

Install a lift or elevator for access to all public areas.

 

$240

 

$10,000

 

$5,000

 

$20,000

Structure

 

The floors are wood and appear to be in good condition.

 

 

Security

There are no security systems in the building. 

Install a metal detector.

 

Install CCTV cameras connected to the courthouse system.

 

Install duress alarms for the prosecuting attorneys.

 

$4,500

 

$4,500

 

 

$800

 

Electrical

The electrical service needs to be upgraded during the renovation.

 

Upgrade the electrical service to the building.

$34,000

Mechanical

The building has an oil-fired boiler.

 

Upgrade the HVAC system and eliminate the oil-fired boiler.

$30,000

Work Safety

No work safety issues were noted.

 

Perform an asbestos study before renovation is begun.

$2,000

Space requirements

There is a need for additional storage and office space for the county. 

 

Renovate the building as needed to provide office and storage space.

$100,000

 

 

 

 

 

 

Subtotal

 

 

$248,540

Soft Costs

Professional fees, permits, surveys, and studies

20%

$49,708

Total

 

 

$298,248

 

 