Mineral
|
Component |
Current
Status |
Recommendations |
Cost
|
|
General
Exterior |
The
Mineral County Courthouse was constructed in the late 1890’s. The approximate size of the courthouse is 18,000
square feet with three stories plus a bell tower, (P1,
P2,
P3,
P4,
P5). The
building is a mixture of styles and materials. The original courthouse is grand with
beautiful brown brick and stonework.
It looks as if there was an earlier red brick addition prior to the
fluted concrete block annex attached to the back. |
|
|
|
Exterior
Walls |
The
exterior of the building is brick. The
building has extensive water damage, moss, mold and staining to the block and
brick located all over the outside of the building. The building shows some evidence of
settlement, (P6,
P7,
P8,
P9). The building has extensive stairstep cracks
on the 2nd floor south exterior wall (P11,
P12). The south, southeast and southwest sides of
the original building have peeling paint (P22,
P23). The overall exterior walls of the building
are in poor condition. The
foundation of the building is stone (P1).
In 1990 they jacked up the building and replaced the south basement
wall. They replaced the wall due to its
continual deterioration and collapse.
The continued collapses led to cracking in the back wall of the
courtroom. Pictures of the courtroom
cracking problem were unable to be taken do to a trial in progress. Otherwise, the interior walls of the building
are in good condition. |
Clean,
and re-point the brick and stone to restore the courthouse. Perform
an engineering study to determine the cause of the cracks on the 2nd
floor south exterior wall. The
interior walls of the courtroom should be repaired, when the cause of
cracking has been eliminated. |
$75,000 $10,000 $ 5,000 |
|
Roof |
The
roof of the original section of the courthouse is pitched with asphalt
shingles that were replaced 1991 and is in good condition, (P1,
P2,
P3,
P4).
The other additions to the courthouse have roofs that are flat with rubber
membrane. They are in good condition. |
|
|
|
Windows
and Doors |
The
windows are wood frame, single pane windows.
They are original to the construction of the building, and are in good
condition, (P25). There are new windows located in the
judge’s chambers and on the lower 2nd floor. They were replaced approximately 6 years
ago. These windows are vinyl frame,
double pane windows in good condition, (P26). The
front entrance door is aluminum frame without panic hardware installed. This door is in good condition and swings
out of the building (P27). |
Install
panic hardware on the entry doors. |
$ 6,000 |
|
Fire
Safety |
The
building does not have a fire alarm or sprinkler system. There are emergency lights in the building
that operate on battery backup, are working properly, and appear to be
located in the proper place. The exit
signs are working and appear to be located in the proper places. The
two staircases in the building are not enclosed by firewalls or fire doors, (P30,
P31,
P32,
P33,
P35). |
Install
a sprinkler system throughout the building. Install
a fire alarm system throughout the building. Install
firewalls and fire doors |
$65,000 $ 5,000 $3,000 |
|
|
There
was one parking space on the right side of the building that had proper
signage but lacked a painted symbol on the ground, (P28). The front entrance of the building was
accessible by a ramp, (P29). Once in the building a lift provided access
from the first to the second floor, (P30,
P31). Building lacks lever hardware and The
building did not have restrooms for handicap access. The
judge’s bench and witness stand are not accessible. |
The
accessible parking space does not comply with Install
new Install
Install new lever handles Install new signage Install witness stand/judge’s bench
lift. |
$100 $10,000 $7,500 $1,200 $18,000 |
Structure
|
The
left wall in the rear of the building has had tension rods installed to keep
the exterior brick from falling off (P23,
P24). Several areas on the front and rear of the
building have major amounts of cracking occurring and need to be studied and
a corrective plan developed. A list
all exterior wall problems is in above exterior wall section. |
|
|
|
Security |
They
do have closed circuit television throughout the building. They also have bulletproof material and
panic buttons on the judge’s bench. Otherwise,
the building did not have metal detectors, guards, or a security alarm
installed. |
Install
an entry-level screening using a walk-through metal detector and an x-ray
machine. Install
an audible alarm, magnetic contacts, and a crash bar on all exit doors except
the main entry. Install
duress alarms beneath the judge’s desk, secretary’s desk, judge’s bench in
the courtroom, hearing table in the jury room, and the clerk’s desk, the
family court judge’s office, the adult and juvenile probation officers
offices, prosecuting attorney’s desk, beneath the receptionist’s desk, and
beneath the table in the conference room.
Duress alarms should be installed beneath the front counter, an office
desk, magistrates’ desks, the magistrates’ assistants’ desks, and the bench
in the courtroom. Prosecution
and defense witnesses should have separate witness rooms and rest rooms to
avoid threats and assaults. The
judge’s bench and clerk’s desk should be protected on the front and sides
that have public exposure with ballistic material. Replaced
all light switches in public areas with key-controlled switches, and breaker
boxes should be locked. Install
a phone line to provide the court and the staff with outside communication in
case of power failure. Apply
window glass tinting to eliminate outside view through the windows in the
courtroom and jury room Remove,
trim, or cut down any bush, shrubbery, or trees surrounding the courthouse
and parking lot, which may provide cover to an assailant. |
$40,000 $7,500 $4,000 $10,000 $6,000 $3,000 $3,000 $3,000 $500 |
|
Electrical |
The
electrical service is overhead and enters the north side of the building from
pole-mounted transformers on the The
lighting for the building (fluorescent and incandescent) is adequate
throughout the halls and offices. |
|
|
|
Mechanical |
Located
in the basement are 2 Burnham gas fired boilers that handle heating, (P50). They are in good operating order and
condition. These boilers feed many hot
water baseboard units throughout the building. There
is a |
We
recommend a central air handling system be installed in the courthouse for
aesthetics and energy efficiency. |
$200,000 |
|
Work
Safety |
No
problems where noted. |
|
|
|
Space
requirement |
Renovation
of the jail would provide for more offices and storage space. |
See
the jail detail report for renovation. |
|
|
Subtotal |
|
|
$482,800 |
|
Soft
Costs |
Professional
fees, permits, surveys, and studies |
20%
of total |
$96,560 |
|
Total
Cost |
|
|
$579,360 |