|
Component |
Current Status |
Recommendations |
Cost |
|
General Exterior |
The building was constructed in the 1930’s and was taken over by the courthouse in 1966. The annex is 2 stories with a basement and has a stone foundation. Exterior – Front P27 - Rear P30 |
The annex needs immediate physical upgrading. |
|
|
Exterior Walls |
The exterior is in fair condition. The brick, on one corner of the building, is showing cracks of up to ½ inch. There appears to be a settlement problem in this area. P33 P34 P35 |
The exterior of the building needs to be cleaned. Exterior masonry cleaning and patch brick and mortar. A structural engineer needs to be consulted for further evaluation of the foundation. |
$ 12,000 $ 1,500 $ 5,000 |
|
Roof |
The roof is flat and is in very poor condition. It is most likely the original roof. P18 P19 Water stands on the roof and leaks through to the offices. P11 Water has been collected in 50 gal trash cans. |
Replace the roof. |
$ 11,000 |
|
Windows and Doors |
The windows are wooden with single glazing. P6 P32 Most windows will not open. Some windows have been replaced with aluminum windows. P4 The doors are aluminum and glass and are easy to open. P2 |
The existing doors and windows provide very little insulation. Replace all exterior doors and windows with commercial grade doors and sashes. |
$ 30,000 |
|
Fire Safety |
There are no fire alarms, sprinklers or exit signs. There are emergency lights. The stairs are not enclosed by fire rated walls or doors. P23 P24 There are two exits in the courtroom but one is blocked. The building does not have two exits on every floor. There is no exit on the second floor. The exit doors swing in the direction of the exit and are equipped with panic hardware. |
Install fire alarm system, sprinkler system and emergency lights. Provide a second exit in the courtroom. Provide an emergency exit from all levels of the building. Enclose the stairwell with fire rated doors. This can be achieved through the renovation process. The estimated cost is included in “Remodel Interior” below. |
See Below |
Structure
|
The building has a stone foundation and is showing signs of settlement in one area. The basement appears to be dry and is in good condition. There is no noticeable damage to the floor system. |
The building needs to be completely remodeled inside. This
would include all new flooring, drywall, trim, paint, interior doors with Remodel Interior of annex (approximately 6,500 sq. feet) |
$860,000 |
|
Security |
There are only two ways into the building. The building has several security cameras and a security system. There are no metal detectors or X-ray machines. There are Duress buttons throughout the building. The judge’s bench has ballistic material. The public restrooms are in the courtroom. |
Restrict all entry to the building to the main entrance. Install a magnetometer and an X-ray machine at the entrance. The existing security system and cameras may be reused. Replace all light switches in the building with keyed switches when remodeling. Remove bathrooms from the courtroom. Replace all interior doors during the renovation process tol make the judge’s chamber, as well as all other offices in the building, more secure. The cost of doing so is included in “Remodel Interior” above. |
$ 40,000 See Above |
|
Electrical |
The electrical wiring and the electric panels in the building are very old and are in poor condition. Many lights reportedly burn out in only one day and several receptacles smoke. |
Replace all wiring, panels and connections during renovation. The estimated cost is included in “Remodel Interior” above. |
See Above |
|
Mechanical |
There is no central air conditioning. Window AC units and space heaters are being used. The heat source appears to be a coal fired boiler converted to gas. P8 |
Replace with a new HVAC system during the renovation process. Cost of mechanical upgrading is included in “Remodel Interior” above. |
See Above |
|
Work Safety |
The wiring, as mentioned above, is a major safety issue. The bathrooms are in very bad condition. Only one out of five toilets is operating properly. The urinals do not work and about half of the sinks do not work. The ceiling is also a major safety issue because it is collapsing in sections from the roof leaks. P13 |
The work area will become much safer after the building’s interior has been renovated and the new roof has been installed. The cost is included in “Remodel Interior” above. |
See Above |
|
Space requirements |
Space is very limited in the annex building. |
Additional space has been recommended for the entire courthouse complex on the main courthouse report. |
See Report |
|
|
The building is accessible from the front through |
Install The building shall become Install elevator |
See Above $ 80,000 |
|
Subtotal |
|
|
$1,039,500 |
|
Soft Costs |
Professional fees, permits, surveys, and studies |
20% |
$207,900 |
|
Total |
|
|
$1,247,400 |