Component |
Current
Status |
Recommendations |
Cost |
|
General
Exterior |
The
original date for the |
|
|
|
Exterior
Walls |
The
exterior walls are stone with a stone foundation. There is no evidence of settlement. There is some missing mortar and water
damage, (P6) |
Clean
and re-point the stone exterior of the building. |
$20,000 |
|
Roof |
The
roof is the original pitched clay tile roof.
It appears to be leaking, (P7, P14). |
|
|
|
Windows
and Doors |
The
windows are the original single pane wood windows. They are in good condition, (P8, P9). The
doors are solid wood doors. They are
in good condition, (P10, P11). |
|
|
|
Fire
Safety |
There
are no fire alarms, sprinkler system, exits lights or emergency lighting. The stairways are open, (P12). There is storage under the stairs, (P13). These things should be removed. No fire system is needed for a museum of
this size. |
|
|
|
Structure |
Once
the roof is repaired, the water damage should be repaired. |
$5,000 |
|
|
Security |
There
is no security in the building aside from locks on the doors and windows. |
|
|
|
Electrical |
The
electrical system is fed from the jail.
It appears to be adequate and in good condition. |
|
|
|
Mechanical |
The
heat is supplied by a boiler in the jail.
There are room air conditioners for the building. |
The
room air conditioners should be replace with a central air conditioner to
improve efficiency and historic correctness. |
$15,000 |
|
Work
Safety |
There
were no work safety issues noted. |
|
|
|
|
The
museum is not accessible. There
is no accessible parking There
is no accessible bathroom |
Install
a ramp. Provide
accessible parking. Install
an accessible unisex bathroom. |
$5,000 $240 $3,000 |
|
Space
requirements |
Additional
storage space is needed. This could come
from a renovation of the jail. |
|
|
|
Subtotal |
|
|
$48,240 |
|
Soft
Costs |
Professional
fees, permits, surveys and studies |
20% |
9,648 |
|
Total |
|
|
57,888 |