Jefferson
County Sheriff’s Offices/Mason Building Detail Report
|
Component |
Current Status |
Recommendations |
Cost |
|
General Exterior |
The Mason Building hoses the parks department, the probation department and the sheriff’s office. The building is two stories plus a basement, (P1) |
|
|
|
Exterior Walls |
The building has tan brick masonry that is in excellent condition. |
|
|
|
Roof |
The pitched asphalt shingle roof is in good condition. |
|
|
|
Windows and Doors |
The doors and window are all wood. Some of them have been replaced with historically correct reproductions. They are all in good condition. |
|
|
|
Fire Safety |
The fire systems are in good condition. There is an alarm system. There are exit lights and emergency lighting. |
|
|
ADA Compliance
|
The building has an entrance ramp that does not have an inside rail. The bathrooms are not compliant. |
Install an inside rail on the ramp. Upgrade the bathroom. |
$1,000 $1,000 |
Structure
|
The building structure appears to be in good condition, (P2) |
|
|
|
Security |
There are no security systems in place. The sheriff mentioned a problem with people visiting the probation officers wandering through the building. |
Install a security system. Provide a way to limit access through the building. Provide security cameras. |
$5,000 $2,000 $5,000 |
|
Electrical |
The electrical system appears to be in good condition. However, there are some exposed wires which should be enclosed in junction boxes, (P3, P4). |
|
|
|
Mechanical |
The mechanical systems are in good condition and adequate for the service.
|
|
|
|
Work Safety |
The only work safety issues noted were the exposed electrical wires. |
|
|
|
Space requirements |
The space appears to be adequate at this time. |
|
|
|
Sub Total |
|
|
$14,000 |
|
Soft Costs |
Professional fees, permits, surveys, and studies |
20% of total |
$2,800 |
|
Total Cost |
|
|
$16,800 |