Component |
Current Status |
Recommendations |
Cost |
|
General Exterior |
The original building was constructed in 1929 (Front, P1; Rear, P2; Left, P3). Additions were made in 1960 and 1962. The exterior of the building is in good condition. The building is two stores plus a basement. The actual square footage is 16,128, including the basement. The foundation is made of concrete and stone with lance wire. There is evidence of foundation settlement. |
|
|
|
Exterior Walls |
The walls are constructed of stone and brick. There is evidence of some water damage and rust stains on the exterior, which should be repaired and removed. |
Clean and repair old courthouse walls. |
$35,000 |
|
Roof |
The roof has water damage. It is both a flat and a pitched roof. The drain system on the flat roof does not work properly. It has a low spot where the water has stagnated and mold has grown. The shingles are in poor condition. The tar on the flat roof is 15 years old. The flashing has rust, (P4, P5, P6, P7, P8). |
Replace flat roof flashing and roof drainage on courthouse. Replace shingle roof. |
$10,000 $5,000 |
|
Windows and Doors |
The windows are aluminum and were replaced in the early 1970’s. The windows show signs of water leakage. Some exit doors swing in the wrong direction (P9). |
Replace exterior windows with signs of leakage. Replace exit doors in courthouse with alarmed doors with panic hardware. |
$55,000 $4,500 |
|
Fire Safety |
There are fire alarms, exit lights, and battery powered lights. There are no sprinklers, strobes, smoke, or heat detectors. The fire marshal does not visit regularly and the extinguishers have expired. There is storage under the stairs. The exit doors on first floor do not swing in the proper direction. There is an open exterior staircase in the back of the building, which does not meet fire codes, (P2). The doors are not equipped with panic hardware. |
Install a sprinkler system in courthouse building. Enclose interior stairs with firewall and fire door. Replace the fire alarm system with one that has smoke and heat detectors, horns and strobes. Install a stair tower on the back of the building. Remove all storage from stairs. Replace fire extinguishers, as needed (Fire extinguishers should be inspected by authorized personnel). |
$38,000 $5,000 $5,000 $40,000 |
Structure
|
The basement has water leakage and damage, (P15, P16). The basement has mildew and mold on the walls suggesting water seepage from the outside (P17). There is a pest problem. The exterminator comes almost every month but there is still a problem with water bugs and termites. The shelves used for storage are rotting. The first floor appears overloaded. There are cracks inside the 1st floor near the assessor’s office. There is excessive water damage throughout the entire building. |
Install French drain on outside of building, and apply rubberized waterproofing to foundation wall to alleviate the water and pest problem in basement. Replace damaged shelving in basement area. Perform a structural analysis for the entire building. |
$80,000 $2,000 $10,000 |
|
|
The courthouse has a handicapped parking space and ramp on
left side of building, (P3). The handicap ramp does not appear to be of
proper slope or length of travel. The
bathroom does not meet |
Renovate Renovate the entrance ramp to be Install proper Install lever handles on doors. |
$10,000 $8,000 $1,000 $3,000 |
|
Security |
There are no security alarms, metal detectors, or closed circuit televisions. The judge’s benches have no bulletproofing or panic buttons. |
Provide entry-level screening composed of a walk through metal detector and x-ray machine. Install a security console, closed circuit television system, and duress alarms for courthouse. Install ballistic protection on all sides of the judge’s bench with public exposure. |
$40,000 $70,000 $3,000 |
|
Electrical |
The electrical systems in the building appear to be adequate at this time. There are open panel boxes that should be replaced with locked panels. All storage in mechanical rooms should be removed. The lighting in the building is inadequate in the hallways. |
Install additional lighting in hallways and keyed light switches and locked electrical panels. Remove stored material from mechanical rooms. |
$10,000 |
|
Mechanical |
There is a gas-fired boiler in the basement, (P18, P19), which is over 10 years old and will need to be replaced in the near future. There is no insulation on the lines, which, poses a burn hazard and reduces efficiency. Window air conditioners are used and there is no central air in the building, (P20, P21). |
Install a new central HVAC system with central air and a new boiler. |
$200,000 |
|
Work Safety |
There are 9x9 tiles on the 2nd floor, which may indicate asbestos. The basement has a damp smell, as well as mold and mildew on the walls and a problem with water bugs . |
Complete asbestos study for courthouse. Complete a mold analysis |
$2,000 $5,000 |
|
General Interior |
Floor tile in the judge’s office is loose and pulling up and needs to be replaced (P22). Evidence of minor water damage is in courtroom from leaks, (P23, P24). There are minor cracks of walls and floors throughout building to be repaired, (P25). |
Repair damaged areas including flooring and walls. |
$10,000 |
|
Space Requirements |
Additional space is needed for the courthouse. They are is currently storage under stairwells, in the mechanical rooms, and in the wet basement. |
An additional 5,000 square feet should be added for storage and offices as needed. |
$725,000 |
|
Subtotal |
|
|
$1,376,500 |
|
Soft Costs |
Professional fees, permits, surveys, and studies |
20% of total |
$275,300 |
|
Total Cost |
|
|
$1,651,800 |